People plan around a move-in date, so here are the honest numbers. This is how long design, City permits, demolition and construction take for a custom home in Vancouver, and what slows a build down. The figures come from the City of Vancouver and from two Vancouver builders who publish theirs. We checked every link on October 29, 2026.
How long does it take to build a custom home in Vancouver?
Plan on 14 to 20 months from first meeting to keys, according to one Vancouver builder. Another says 19 to 36 months, because it also counts finding a lot and hiring a team. Construction alone runs 10 to 14 months at the first and 13 to 18 months at the second, for 3,500 to 5,000 square feet.
Both ranges are builder estimates, not guarantees. The spread comes from the lot, the size of the house, the finishes and the permit queue. If you already own your lot, you skip the 4 to 6 months of planning that the longer estimate counts, which includes choosing a location and hiring a team. Here is how the stages stack up.
| Stage | Typical time | Source |
|---|---|---|
| First consultation | 1 to 2 weeks | A Vancouver builder |
| Design and planning | 8 to 12 weeks | A Vancouver builder |
| City permit processing, single-detached home | 160 days in 2025 | City of Vancouver |
| Demolition, if needed | A week or less in most cases | A Vancouver builder |
| Construction | 10 to 14 months | A Vancouver builder |
How long does design take?
Expect 8 to 12 weeks for design and planning, after a first consultation of one to two weeks, according to one Vancouver builder. Another says one to three months or more, depending on the size and complexity of the home. The biggest variable is how quickly you make decisions, not how fast the drawings are produced.
One Vancouver builder notes that clients who finish design quickly make finish decisions in batches, not one fixture at a time. We see the same thing. Our designers, interior designers and project managers work in the same office, so the drawings, the finish selections and the budget move together. That keeps a late change from becoming a late surprise.
How long does the City of Vancouver take to issue a permit?
The City reports that permit processing time for single-detached homes fell 36 percent, from 250 days in 2022 to 160 days in 2025. That is a little over five months. Laneway houses fell from 200 days to 100 days. Your own timeline depends on how complete your drawings are and how fast comments are answered.
The City's building permit page lays out the steps. A separate development permit comes first for large projects and where zoning relaxations are needed. One Vancouver builder puts permits at 3 to 4 months or more across Vancouver, the North Shore and Burnaby. Another builder calls permit delays the most common cause of schedule slips and the most preventable. Its advice is to submit a complete, code compliant application the first time and answer the City's comments quickly. We build our permit sets the same way.
What has to happen before the permit is issued?
Your builder must be licensed by BC Housing and register the home for warranty insurance. BC Housing then issues a New Home Registration Form, which you need before the building permit. If an older house is coming down first, a demolition permit is required for any residential building built before 1950.
BC Housing sets out the registration step. The City's Green Demolition By-law adds conditions to those pre-1950 demolitions. At least 75 percent of the materials, by weight, must be reused or recycled, and 90 percent for a character house. A house built before 1910, or a heritage-listed house built before 1950, must be deconstructed, with at least three tonnes of wood salvaged. One Vancouver builder adds that hazardous materials in an old house can add time before it comes down.
In First Shaughnessy the process has more steps. A development permit is required for new development and for any demolition, according to the Official Development Plan. The First Shaughnessy Advisory Design Panel reviews applications, and the City's checklist says an applicant may be asked to present to it. We cover the heritage side in our guide to restoring or rebuilding a character home.
How long does construction itself take?
Construction commonly takes 10 to 14 months at one Vancouver builder, and 13 to 18 months at another for larger homes of 3,500 to 5,000 square feet. The second builder breaks the work into stages: site preparation takes 1 to 2 weeks, the foundation about a month, and framing 1 to 3 months.
The finishing stretch is the longest part to watch. The first builder schedules finish work, meaning cabinetry, flooring, tile and paint, between weeks 28 and 44 of a 56 week build, and says it is where most change orders happen. A finished set of selections before construction starts keeps that stretch on schedule.
What slows a custom home build down?
One Vancouver builder names permit delays as the most common cause of slips, and says finish work is where most change orders happen. Hazardous materials in an old house and heritage review can add time too. Almost all of it can be planned for, which is why we plan before we build.
Our approach is simple. We finish the drawings before we submit them. We ask you to settle finishes in batches. We keep design, pricing and construction under one roof, so the person who prices the house is the person who builds it. None of that removes risk, but it moves the risk to the front, when changes are cheap.
Frequently asked questions
How long does a custom home take from the first meeting to move-in?
Two Vancouver builders give different answers. One puts it at 14 to 20 months. The other gives 19 to 36 months because it also counts finding a lot and hiring a team. Your own schedule depends on the lot, the size of the house, the finishes and the permit queue.
How long does the City take to issue a laneway house permit?
The City of Vancouver reports that laneway house permit processing fell from 200 days in 2022 to 100 days in 2025.
When should I hire a builder?
Early. Hiring a builder can take one to two months or more, according to one Vancouver builder, and another advises calling a builder before you buy a lot. We would say the same. A short conversation before you buy or sign off drawings costs little and can save months.
Do I need a permit to demolish my old house?
A residential building built in whole or in part before 1950 needs a demolition permit under the City's Green Demolition By-law, with reuse and recycling conditions. Confirm the age and status of your house with the City before you plan the schedule.
Does design-build make the schedule shorter?
It can. When design, pricing and permit drawings come from one team, the builder sees cost and constructability while the drawings are still open, and fewer questions come back from the City or the trades.
Want a schedule built around your lot? Book a complimentary consultation with Tavan Group and we will map your design, permit and build stages together.
Questions people ask
How long does a custom home take from the first meeting to move-in?
Two Vancouver builders give different answers. One puts it at 14 to 20 months. The other gives 19 to 36 months because it also counts finding a lot and hiring a team. Your own schedule depends on the lot, the size of the house, the finishes and the permit queue.
How long does the City take to issue a laneway house permit?
The City of Vancouver reports that laneway house permit processing fell from 200 days in 2022 to 100 days in 2025.
When should I hire a builder?
Early. Hiring a builder can take one to two months or more, according to one Vancouver builder, and another advises calling a builder before you buy a lot. We would say the same. A short conversation before you buy or sign off drawings costs little and can save months.
Do I need a permit to demolish my old house?
A residential building built in whole or in part before 1950 needs a demolition permit under the City's Green Demolition By-law, with reuse and recycling conditions. Confirm the age and status of your house with the City before you plan the schedule.
Does design-build make the schedule shorter?
It can. When design, pricing and permit drawings come from one team, the builder sees cost and constructability while the drawings are still open, and fewer questions come back from the City or the trades.
- City of Vancouver: Permitting is getting easier in Vancouver with multiplex approvals now 50% faster
- City of Vancouver: Building permit
- Major Homes: From Lot to Keys, Our 14 Month Custom Home Build Timeline
- Hasler Homes: How Long Does It Take To Build A House? A Timeline for 2025
- BC Housing: Register a New Home
- City of Vancouver: By-law No. 12239, amending the Green Demolition By-law
- City of Vancouver: First Shaughnessy District Development Permit Checklist
- City of Vancouver: Heritage Conservation Area Official Development Plan
Design-build custom homes on the west side, one team from the first sketch to the keys.
How we do it →